Traffic cut in avenida Fernando de los Ríos and side streets

Due date for traffic cuts in avenida Fernando de los Ríos and side streets will be carried out as follows in this plan:

C/ BALADÍES (section between C/ La Tahá and C/ Omeya).- Total traffic cut from 21/10/24 to 03/11/24, with free access to garages in the area.

Crossroad with C/ LA TAHÁ (at the high of C/ Baladíes).- Total traffic cut three working days from 04/11/24, reopening traffic at the end of day and free access to garages in the area.

C/ BALADÍES (section between C/ Omeya and C/ Emir).- Total traffic cut between 07/11/24 and 20/11/24, with free access to garages in the area.

Crossroad with C/ EMIR (even number side).- Partial traffic cut leaving one lane open at any moment,between 21/11/24 and 27/11/24.

Crossroad with C/ EMIR (odd number side).- Partial traffic cut leaving one lane open at any moment,betweel 28/11/24 and 04/12/24.

SERVICE ROAD AVDA. FERNANDO DE LOS RÍOS (extension C/ Baladíes between C/ Emir and C/ Muladíes).- Total traffic cut for four weeks from 05/12/24, only on working hours reopening traffic at the end of works.

AVDA. FERNANDO DE LOS RÍOS (between C/ Muladíes and C/ Baden Powell).- Partial traffic cuts for two weeks from 13/01/25, leaving one lane open to traffic wide enough for big dimensions vehicles.

Crossroad AVDA. FERNANDO DE LOS RÍOS (at the high of C/ Baden Powell).- Partial traffic cut between 27/01/25 and 31/01/24 (reopening traffic for the weekend), not affecting both lanes at the same time and leaving a lane wide enough for big dimension vehicles.

File 34.788/24