Due date for partial traffic cuts in San Antón street number 62 will be within 18 months according to following plan:
Earth movements and foundation works at ground level six times, 3-5 hours duration except for the empting of land works will be 8 hours on a Saturday. Cuts must be carried out in the afternoon at 16:00 hours except empting of land works that will start at 8:00 hours on Saturday.
Structure at ground level: partial traffic cut fifteen times, 2- 3 hours duration, in afternoon hours from 16:00 hours.
During all works: punctual traffic cuts maximum duration 30 minutes for the supply of materials and tools between 7:00 and 8:00 or between 16:00 and 17:00 hours.
File 43.676/24