Total traffic cut in Jarrería and Escutia streets will be from 18/02/25 to 15/04/25 according to the following plan.
Concrete phase: Concrete works will last three hours maximum each, between 9:30 and 13:30 hours, or at 16:00 hours, removing work vehicles once works are done. Traffic will be regulated by operators.
Structure phase : Intermittent traffic cuts thirty minutes long, between 9:30 and 13:30 hours, and at 16:00 hours. Street can not be closed to traffic when loading and unloading works are not being carried out.
Traffic will be regulated by operators to guarantee access to garages in the area. Traffic cut should not be carried out in school peak hours.
File 6.563/25