Due date for total traffic cut in 39 camino del Sacromonte will be according to following planning:
If works can be arranged involving partial traffic cut: Partial traffic cut, keeping one lane open to traffic for big dimension vehicles (public transport service) will be two workind days on Tuesday, Wednesday or Thursday on the following fortnight from date of notification between 9:00 and 19:00 hours, reopening traffic at the end of working day, placing a sheet metal.
If works must be arranged involving total traffic cut in Camino del Sacromonte: Total traffic cut wil be carried out only from 7:00 to 19:00 hours one Sunday on the following fortnight from the date of notification.
Conglomerate works will be done on off peak hours (from 9:00 to 13:30 or from 16:00 to 19:00 hours) on a working day, just as necessary, with alternate pass of traffic regulated by work operators.
Traffic cut will be just as necessary to carry out works, reopening at the end of each working day, with free access to garages in the area.
File 16.654/26