Due date for partial traffic cut in 3 Ancha de Capuchinos St occupying reserved lane according to following plan:
Structure phase: during the following 5 months 60 downloading of material (3 per week) between 10:00 and 17:00 hours, reopening street as soon as possible.
Rest of works (mansory works and finishing works): during 11 months starting from structure phase, 90 downloading of material (twice per week) between 10:00 and 14:00h or between 16:00 and 18:00 hours, reopening traffic at the end of works.
File 2026/16161F